The Present

Welcome to the Boulder Pointe Condominiums
Construction Zone. Boulder Pointe is a
Page Development project on Manasota Key.
This page shows work that is current at the complex. The further down the page you go, the farther back in time you are looking. We will be updating this page on a regular
basis as the work there continues.
Last updated: July 31st, 2007
Boulder Pointe is a Gulf front condominium under
construction in the
The main attraction is the beach; this is what it’s
all about. The views from the Gulf Front
buildings are spectacular.

July 2007

All of the building exteriors have now been completed
by the summer and the exterior amenities are being installed and finished up. The roadway is in now, the base for the tennis
court has been compacted and is ready for paving, and the drainage system is in
place.

Under the buildings the paver brick system has been installed.
It is left with a fine covering of sand to
help protect it while construction continues.

The pavers around the gulf front pool will make for a
huge sitting area. The second swimming pool
by building 3 has been poured and now is ready for the quartz finish. The dune crossover system of
stairs leading down to the beach have now been completely rebuilt.

Here we see the pad for the tennis court behind building
3 and the retention system on the north side of the main entrance.

Here we see one of the custom
kitchens. This unit has all wood maple cabinets
and dark granite countertops.

Carpeting and tile inside the units has now been completed.
The interior trim has now been installed
and painted.

On the porches, the handrails
have now been installed.

This project is about complete now. The units are being made ready for delivery.
June 2007

During the month of June of 2007 most of the interiors
of buildings 1 and 2 were completed. Outside
the site work is really moving along quickly. The gulf front swimming pools has been completed
and work on the paver brick deck that will surround it has commenced.

Building 3 shown here at the
beginning of June was completed on the exterior this month.

Tile is installed on the porches
overlooking the

Building 2 interior finishes
are installed. The buildings are nearing
completion.
May 1, 2007

The complex is really coming together now. The exterior of both the Gulf front buildings
have been completed and all the scaffolding has been removed. The grounds have been cleared and next week
the site improvements around the exterior of the complex will commence.

The parking level under
building 1 is now prepared for the paver brick finish which will go on next.

Inside the units, the finish
trim is going in. The kitchen cabinets
have been set and the bath fixtures are going in.

Finished door casings are
being installed

Out by the Gulf Pool the new
filtration system has been installed and more work done on the landscaping.

It is getting close now. Current estimates are that building 1 should
be completed around the end of June, with building 2 being finished the end of July
and the final building about 30 days after that.
April 15, 2007

Building 1 overlooking the beach is nearing
completion on the exterior. The
scaffolding is coming down now that the building exterior has been stucco
finished and painted. The roof drainage
system is now in place and in the foreground we see the Gulf swimming pool now
being prepared for completion.

Here we see the front
walkway from the elevator on the 3rd floor to the front door entries
of the 2 units.

Inside building 1 the interior ceilings and walls
have now been painted. Trim carpentry
comes next along with the cabinets and bath fixtures.

Building 2 on the gulf is
nearing completion of the exterior

Building 2 interiors are in the drywall finish
stages. Here we see a 2nd
floor unit that has been taped and is now ready for primer paint. This building is running about 30 days behind
Building 1 in the completion schedule.

Here we see the exterior of
the beachfront side of Building 2. We are
seeing steady progress every day at the complex which scheduled for completion
during the late summer and early fall of 2007.
March 1, 2007

The buildings are closed in and in the process of
being stucco finished. Windows and doors
have been installed in both of the gulf front buildings. Waterproofing and wire lathe are installed to
have the stucco finish applied.

Archtictural detailing is installed for
the window and door trim.
Interior rough components
are now installed

The exterior of the building
is being stucco finished


The building exterior is
taking shape

The General Contractor

Progress through February
2007

December 30, 2006

Both
of the beachfront buildings are shown here with exterior walls being
erected. Inside the building structural
steel walls are set, ceiling supports have been installed and electric,
plumbing and air conditioning systems are being roughed in.

Interior
finish selections have now bee made by the unit owners and custom installations
and requests are being included wherever possible.

The front entries to the
units from the elevator station.

Boulder Pointe Codnominiums is coming together very nicely now.

This
is a very busy place these days. Contact
your sales agent at Manasota Key Realty to arrange for your tour of the
buildings. Several select units are
presently available.
Back in October 24, 2006

All 3 of the structures now stand complete to the
rooflines and the interior partitions are being set. The interior walls are all steel reinforced
partitions designed to withstand hurricane force wind loads.

Building 2 is now surrounded
by scaffolding as well as building 1

Back in September 2006

Scaffolding now surrounds Building 1 as of the last
week in August of 2006. The staircases
have been installed and poured, all concrete floor and roof systems are now in place
and the interior layouts are going in.

These are going to be large
homes. Big Rooms with Big Views

The South Building 2 has
topped out by August 2006 and Building 3 is following closely behind.

Exterior walls start going
in during the month of September.

A top
floor view towards the north.

The view across Manasota Key
towards
To see more about the early
stages of construction, please go to the linked webpage
It will give you an in-depth view of the entire
construction process.
Check back with us again soon to see how
the buildings at